Transport NSW to fine Spanish consortium Acciona $500,000 for every day light rail is delayed
Constance seems to ignore the fact that it’s tax payers wearing the cost of his poor management of our transport network… not him.
THE Spanish consortium building Sydney’s light rail will be forced to pay at least $500,000 for every day it misses the project’s 2019 opening date, The Daily Telegraph has been told.
It comes as Transport Minister Andrew Constance yesterday savaged ALTRAC for running more than a year behind schedule on the construction of key sections of the line.
Mr Constance said he expected them to “get on with the job” and meet the April 2019 light rail operation date.
“It’s fair to say (the government) is an unhappy customer at the moment,” he said.
“We expect better.”
Subscribe to Bus Express
cforms contact form by delicious:days
Tag Cloud
Baird government
BBQ
Belmont
Berejiklian
Bus
Bus Division
bus privatisation
Chris Preston
depot
dispute
Drivers
EA
Gary Way
gas buses
Hunter
IR
IRC
Know Your Rights
Light Rail
Mike Baird
negotiations
Newcastle
Newcastle Herald
NSW Government
O'Farrell
O'Farrell's Law
Opal
pay
pork chop
privatisation
rally
Randwick
RTBU
RTBU Tram and Bus Division
safety
STA
STA Buses
sydney bus services
Sydney CBD
Tram News
Transport for NSW
Transport Masterplan
uniform
Unions NSW
workplace
RSS Feed
- Crisis talks: next steps 22 February, 2018
- Transport NSW to fine Spanish consortium Acciona $500,000 for every day light rail is delayed 21 February, 2018
- Longer trips for light rail passengers without green-light priority 21 February, 2018
- Sydney light rail MESS 20 February, 2018
- Huge crowd demands review of Newcastle and Lake Macquarie’s new bus timetable 19 February, 2018